FIGURE 35
STEP 34
• Assemble one 3-1/2” PULLEY (79) around the PEC DEC CABLE (93) and to the PULLEY BRACKET (5) using one 3/8 X 1-3/4”
BOLT (36) and one 3/8” LOCKNUT (48) as shown in FIGURE 34.
24
FIGURE 34
93
STEP 35
• Slide the ends of the PEC DEC CABLE (93) into the bushings on the PEC CAMS (24) as shown on FIGURE 35.
• Lay the PEC DEC CABLE (93) over the pulleys and under the cable retaining clips in the CENTER PULLEY BRACKET (21) as
shown in FIGURE 35. (NOTE: The bolt holding pulley and cable retaining clips may need to be loosened to align cable
retaining clips with cable.)
24
79
48
5
93
36 3/8 X 1-3/4”
21