Precor 723e Stepper Machine User Manual


 
Page 8
Rope (718e only)
Plastic wire tie (723e only)
Upright support
Diagram 5
Pull reed switch cable through
upright support.
Reed switch cable
Reed switch cable connector
2. Feed Reed Switch Cable through Upright Support. (Diagram 5) Remove
the bolts from the base column support (short column) and set them
aside. The gasket should hang on the reed switch cable. Take the following
steps to install the reed switch cable:
a. Cut the wire tie from around the reed switch cable and, if necessary,
gently pull the cable out of the roller guard. Place the short column
near the upright support so that the gasket and roller guard face the
rope.
b. Ask an assistant to hold the base column support. This lets you have
both hands free to manipulate the rope (718e only)/plastic wire tie
(723e only) and cable.
c. Securely tape the reed switch cable connector to the
end
of the rope
(718e only)/plastic wire tie (723e only) and feed the cable through the
upright support (long column) as you carefully pull the rope (718e
only)/plastic wire tie (723e only) out from the top. Tape the reed
switch cable to the top of the upright support and set the rope (718e
only)/plastic wire tie (723e only) aside. (On the 718e you will use the
red rope in step 12.)
Note: You may need to tip the climber onto its side if the cable
disengages from the rope/plastic wire tie. A hex key is helpful in
locating the cable inside the column and in pulling it through the hole
at the top.