Q02
Q02
Q01
Q01
Q03
Q03
Q07
Q07
Q06
Q06
Z36
Z36
7
STEP
• Align holes in rear shield (Q03) with the
holes in the brackets (Q08 & Q09) on the
back side of the weight stack; loosely
secure using 8 bolts (M5x10). Take the left
(Q01) side shield and repeat on front side
of weight stack tower using five bolts
(M5x10). Tighten interior brackets. Attach
the right (Q02) shield to the tower using
five bolts (M5x10). Tighten all bolts.
• Place two slip-on nuts (Z36) over the
holes on the side of the weight stack
tower. Snap two halves of top cover (Q06
& Q07) together. With tallest point facing
the rear of the machine, place the
assembled top covers on top of the weight
stack tower and secure using six bolts
(M5x15).
RED BAG