Spalding 21196804 Fitness Equipment User Manual


 
10
P/N 21196804 10/04
4
3
Fill hole completely with concrete.
6.
1" (2.54 cm)
5
1
" (2.54 cm)
7.
Tamp down concrete to release air pockets and build drainage hill. Level pole section in all directions
several times while concrete is curing.
1" (2.54 cm)
SIDE VIEW
DRAINAGE HILL
IMPORTANT!:
CONTINUE ON TO NEXT STEP.
DO NOT
WAIT FOR CONCRETE TO CURE.
IMPORTANT!: WAIT A MINIMUM OF 24 HOURS BEFORE GOING ON TO NEXT STEP.
CONCRETE MUST
CURE.
PLAYING SURFACE
Make a reference mark
here for anti-skid tape.
NOTE A:
Keep flange pushed down
to concrete and leveled.
NOTE B: